Gina Krog · Equinor
Planning Specialist
Planning for a subsea and topside EPCI contract. The scope covers studies, engineering, procurement, prefabrication, installation and mechanical completion.
Experience
A selection of my assignments in oil and gas, offshore wind, process industry and rail. My roles range from detailed planning to planning leadership and offshore coordination.
Project values refer to publicly announced contracts or investments. Each amount states its scope and year. Foreign currency amounts are converted to Norwegian kroner using the annual average exchange rate for the announcement year and are not adjusted for inflation.
Planning Specialist
Planning for a subsea and topside EPCI contract. The scope covers studies, engineering, procurement, prefabrication, installation and mechanical completion.
Construction and Completion Planner
Site planning for greenfield and brownfield work. Construction, mechanical completion and commissioning across civil, piping, mechanical, electrical, instrumentation and insulation disciplines.

Engineering and Completion Planning Lead
Responsible for engineering and completion planning for DolWin5 / DolWin epsilon, an EPCIC delivery to TenneT. Aibel held responsibility for the contract within the consortium with Keppel FELS. The project covered engineering and procurement, construction and mechanical completion in Singapore, followed by outfitting, commissioning and offshore installation through Haugesund.

Planning Manager
Leading site planning for engineering, construction, mechanical completion and commissioning. The scope included both greenfield and brownfield work.

Planning Lead
Leading site planning from engineering and construction through to mechanical completion and commissioning, in a project involving both greenfield and brownfield work.
Planning Specialist
Project planning and reporting for offshore flowline projects and maintenance, modifications and operations (MMO) assignments. The work covered planning and follow-up across several projects.
Completion Planner / Offshore Coordination Manager
Completion planning at Aibel’s yard in Haugesund before tow-out and offshore installation. Followed by planning and coordination of offshore work, with follow-up of materials, tools, qualified personnel, permits and certificates.

Senior Project Planner
Planning accommodation upgrades on Statfjord A, B and C and Draupner. Several projects from studies to completion, using SAP and ProCoSys.
Senior Planning and QA Coordinator
Coordinating facilities and interfaces for maintenance, construction and building extensions, including production and test facilities. Contributed to the introduction of Safran Planner to replace Microsoft Project and to the development of shared working methods in the planning department.
Planning Department Lead / Project Area Lead / Project Manager
Leading planning for the prefabrication and installation of flowlines and gas lines. Subsequently managed flowline projects on Ekofisk K, B and A, with a multidisciplinary team of 13 and responsibility for planning prefabrication and installation.
Project Planner
Multidisciplinary planning of the main pipe racks, a scope of approximately 100,000 work hours. Activities covered prefabrication and assembly by subcontractors in Belgium and installation at Nyhamna.
Modernisation of SJ’s X2000 trains in Sweden. ABB’s part of the programme covered upgrades to the trains’ computer, propulsion and control systems. SJ also announced an interior renewal as part of the overall investment.

A practical foundation
I started as a plateworker and platefitter in 1985. Work preparation and planning followed from 1990, before I moved into project planning and leadership roles.
My background also includes production management at MPM, procurement planning at Kværner Eureka and teaching mechanical subjects at Sauda Upper Secondary School.
View my full career historyMy CV covers my full background, from hands-on work at the yard to planning leadership and the follow-up of complex projects.